Building Future: Referendum Progress
Coming Soon: Full-Day Kindergarten 2022-23
Ground Breaking
On May 17, 2021, the D34 Board of Education, Village Representatives, administrators and students broke ground at Lyon, Westbrook and Henking elementary schools and Springman Middle School.
An Overview
On March 17, 2020, the community approved a referendum for $119 million to allow District 34 to repair, replace and update our buildings.
This successful referendum signals that residents understand the importance of reinvesting in the school district’s capital assets. The impact of the referendum will positively impact the community for decades to come, and it will be felt at every school, in every classroom, by every District 34 student. We recognize that we are tasked with Building Future.
School Construction Schedule
Lyon Timeline
- Week of 6/7/21 - 6/11/21
- Week of 6/14/21 - 6/18/21
- Week of 6/21/21 - 6/25/21
- Week of 6/28/21 - 7/2/21
- Week of 7/5/21 - 7/9/21
- Week of 7/12/21 - 7/17/21
- Week of 7/19/21 - 7/24/21
- Week of 7/26/21 - 7/31/21
- Week of 8/2/21 - 8/7/21
- Week of 8/9/21 - 8/14/21
- Week of 8/16/21 - 8/21/21
- Week of 8/23/21 - 8/28/21
- Week of 8/30/21 - 9/4/21
- Week of 9/6/21 - 9/11/21
- Week of 9/13/21 - 9/18/21
- Week of 9/20/21 - 9/25/21
- Week of 9/27/21 - 10/2/21
- Week of 10/4/21 - 10/9/21
- Week of 10/11/21 - 10/16/21
- Week of 10/18/21 - 10/23/21
- Week of 10/25/21 - 10/30/21
- Week of 11/1/21 - 11/6/21
- Week of 11/8/21 - 11/13/21
- Week of 11/15/21 - 11/20/21
- Week of 11/22/21 - 11/27/21
- Week of 11/29/21 - 12/4/21
- Week of 12/6/21 - 12/11/21
- Week of 12/13/21 - 12/18/21
- Week of 12/20/21 - 12/25/21
- Week of 1/10/22 - 1/15/22
- Week of 1/17/22 - 1/22/22
- Week of 1/24/22 - 1/29/22
- Week of 1/31/22 - 2/5/22
- Week of 2/7/22 - 2/12/22
- Week of 2/14/22 - 2/19/22
- Week of 2/21/22 - 2/26/22
- Week of 2/28/22 - 3/5/22
- Week of 3/7/22 - 3/12/22
- Week of 3/14/22 - 3/19/22
- Week of 3/21/22 - 3/26/22
- Week of 4/4/22 - 4/9/22
- Week of 4/11/22 - 4/16/22
- Week of 4/18/22 - 4/23/22
- Week of 4/25/22 - 4/30/22
- Week of 5/2/22 - 5/7/22
- Week of 5/9/22 - 5/14/22
- Week of 5/16/22 - 5/21/22
- Week of 5/23/22 - 5/28/22
- Week of 5/31/22 - 6/4/22
Week of 6/7/21 - 6/11/21
Week of 6/14/21 - 6/18/21
Week of 6/21/21 - 6/25/21
Week of 6/28/21 - 7/2/21
Week of 7/5/21 - 7/9/21
Week of 7/12/21 - 7/17/21
Week of 7/19/21 - 7/24/21
Week of 7/26/21 - 7/31/21
Week of 8/2/21 - 8/7/21
Week of 8/9/21 - 8/14/21
Week of 8/16/21 - 8/21/21
Week of 8/23/21 - 8/28/21
Cibulka
- Prep/pour SOG
Albrecht
- Temp seed black dirt pile
- Work with AH on hauling spoils for trap
M/I
- Taking delivery on the 26th of deck and joists, will get started on the following Monday
Carey
- UG electric will wrap up
AJ
- Storm trap to start being excavated
- Existing downspout connections
- Tie in storm outside building
Week of 8/30/21 - 9/4/21
Week of 9/6/21 - 9/11/21
Week of 9/13/21 - 9/18/21
AJ
- Set storm trap on Friday the 17th
- Tie in the storm from building so can backfill
M/I Steel
- Will finish decking on end of day Wednesday
Doherty
- Start snapping lines and framing CFMF. Exterior delivery Monday morning start framing Tuesday
- Compass will be out Monday morning to layout
Jensen's
- Layout alongside Doherty-make sure pipes are in walls
- Set RD's starting Wednesday the 15th
FE MORAN
- Curbs to be set on deck starting the 15th
Cibulka
- Need to patch back sidewalk on NW side (school needs walking path back)
- Pour strom trap base on Wednesday
- Pour MPR slab on Friday
Albrecht
- Stone for MPR on Tuesday
Sebert
- Install SOD where sanitary line went in
Spancrete/Continental
- Will be onside Monday to remove the bracing in the MPR
Week of 9/20/21 - 9/25/21
Doherty
- Continue framing walls
Cibulka
- Finish pouring misc. sections of SOG
Carey
- Start layout ad establishing runs
Jensen's
- Working on setting/connecting RD's and layout
FE Moran
- Setting curbs, portals whatever is needed before roof insulation starts
- Confirmed per RFI 33 that pip supports will lay on top of insulation
AJ
- Storm trap date pushed to be set 9/23 (Thursday)
Spancrete
- Fix splice detail around perimeter of precast any day after Tuesday
- Patch holes from bracing
Week of 9/27/21 - 10/2/21
AJ
- Will finish strom trap, backfilling and connecting pipes at each end
- TIe in storm on east side
- Downspout connections in courtyard approved
M/I
- Missed bent angle above windows needs to be installed
Spancrete
- Fix splice detail around perimeter of precast
- Patch holds from bracing
Doherty
- Continue framing and start sheathing exterior walls for mason to get started
- IWS to spray fluid applied air barrier
Hargrave
- Delivery of frames
FE MORAN/AMBER
- 9/30 curbs to show up and be installed
Jensen's
- Start rough
Week of 10/4/21 - 10/9/21
Week of 10/11/21 - 10/16/21
DCG/Alloy/Filotto
- Wood blocking for lower roofs
- Kettle set up on east haul road and crane in courtyard
- Flashing to start on roof walls
- Wrap up the MPR roof this week
- Filotto to get rolling on temping in both shingled roofs
AMBER
- Keep working on handing ductwork
- Curb work
Doherty
- Keep on framing - interior and exterior walls/dormers on north elevation
- Sheathing, air barrier and rigid insulation ongoing
Jensen's
- Rough plumbing
Hargrave
- Once an answer on spray foam then grames can be set
Carey
- Rough Electric
FE Moran
- Working hand in hand with Amber on curbs
- Layout boiler room - access on 10/15. No school day
Nelson FP
- Will start FP pipe in MPR
AJ Oleson
- Finish work with tie in storm on east side
- Set structures on top of storm trap
Albrecht
- Stone southside
- Temp seed dirt pile on south
M/I
- Bent angles for above windows (RFI 43)
- Angle at vest 101
Mastership
- Mobilize by end of week
Week of 10/18/21 - 10/23/21
DCG/Alloy/Filotto
- Wood blocking for lower roofs
- Flashing to start on roof walls after iWS
- Filotto to get rolling on temping in both shingled roofs per RFI 44 on Monday
- DCG to continue lower flat roofs
- Build dividers
Amber
- Keep working on ductwork
Doherty
- Keep on framing interior walls
- Sheathing, ongoing on north elevation
- IWS needs to keep going on air barrier (weather)
Jensen's
- Rough plumbing
Hargrave
- Will be setting door frames and start to temp up openings
Carey
- Rough electric
FE Moran
- Continue layout and piping
Nelson FP
- Rough FP
AJ Oleson
- Finish work with tie in storm on east side
- Set structures on top of storm trap
M/I
- Bent angles to be installed in all eight locations on Tuesday
Mastership
- Mobilize by end of week
Week of 10/25/21 - 10/30/21
DCG/Alloy/Filotto
- Wood blocking
- Cap sheet
- Install skylights
- Filotto to keep working on shingled roofs
Amber
- Keep working on hanging ductwork
- DOAS UNITS TO BE ONSITE WITH CRANE ON THURSDAY (10/28)
- Get drops set inside RTU's
Doherty
- IWS to continue work with air barrier
- Insulation and frame for inside of DOAS units
- Start framing walls at gulley of roof for wall panels
Jensen's
- Rough plumbing
- Set hose bibs before brick starts
Hargrave
- Will be setting door frames
- Start to temp up exterior openings
Carey
- Rough electric
FE Moran
- Continue layout and piping
- Investigate work inside existing boiler room
AJ Oleson
- Finish work with tie in storm on east side
- Set structures on top of storm trap
M/I
- Maybe one day to finish up decking dormers and clean up
Mastership
- Start mobilizing on Tuesday
Week of 11/1/21 - 11/6/21
DCG/Alloy/Filotto
- Cap sheet
- Install skylights
- Filotto to keep working on shingled roofs
AMBER
- Keep working on hanging ductwork
- DOAS units were set on Friday
Doherty
- IWS to continue work with air barrier
- Start framing walls at gulley of roof for wall panels
- Frame soffits along exterior
Jensen's
- Rough plumbing
- Set hose bibs before brick starts
Hargrave
- Temp up exterior openings with plywood and plastic
Carey
- Rough electric
FE Moran
- Prep for temp heat
- Roughing
AJ Oleson
- Set structures on top of storm trap
- Backfill storm line connect on east
M/I
- Supply lintels for brick
Mastership
- Start in courtyard
Week of 11/8/21 - 11/13/21
DCG/Alloy/Filotto
- Alloy metal wall panels
- Z-flashing along perimeter
- Filotto working on shingles
AMBER
- Ductwork should be wrapping up
Mastership
- Courtyard brick and stone sills
Doherty
- Air barrier work
- Insulation of walls once watertight (should be this week)
Jensen's
- Plumbing rough
Carey
- Electric rough
FE Moran
- Rough piping continue
Week of 11/15/21 - 11/20/21
DCG/Alloy/Filotto
- Flashing and coping work will be ongoing
- Shingles will continue
Mastership
- Face brick in courtyard
- M/I supposed to deliver lintels this week
Doherty
- Insulation of interior and exterior walls once roof if watertight
MEPFP's
- Continue roughing maybe start looking to get in wall inspections
AJ
- Once brick is far enough along in VY then we can connect downspouts
Week of 11/22/21 - 11/27/21
DCG/Alloy/Filotto
- Filotto to start installing shingles
- Wood blocking and fascia plywood
- NW corner
- Skylights and roof hatches
Doherty
- Start skylight framing
- Bench framing once spray foam is far enough along
- Drywall start by end of month
- Spray foam ongoing
- Backing in classrooms
AMBER
- Ductwork and hanging fan coils
Jensen's
- In-wall water piping
- Flush valve/rab bar dilemma
Carey
- Rough electric
- Subs got started
FE Moran
- Rough piping
- Cap curb with no unit
- Welding gas pipe on roof
- Temp control guy to get started sooner than later
M/I
- Splice detail per $3.00 detail 5
Mastership
- Working on brick in courtyard
- CMU walls in MPR on rain days
Week of 11/29/21 - 12/4/21
In wall inspections before drywall
DCG/Alloy/Filotto
- Alloy metal wall panels
- Filotto should be close to complete
AMBER
- Mech rough almost complete
Mastership
- Courtyard brick and stone sills to starts
Doherty
- Insulation of walls
- Spray foam almost complete
- Skylight framing
- Drywall uppers
Nelson
- Once skylight framing is complete Nelson will get back onsite
Jensen's
- In wall water piping
Carey
- Electric rough
FE Moran
- Roughing
Week of 12/6/21 - 12/11/21
DCG/Alloy/Filotto
- Filotto ongoing work with shingles
- DCG to fix NW corner
- Skylights and Roof hatches
- Set RD Covers
Doherty
- Skylight framing
- Drywall starts Tuesday
- Sheath dormer side walls for roofer
- In-wall insulation
AMBER
- Hanging fan coils
Jensen’s
- In-wall water piping
- Insulating water pipe
- Air testing
Carey
- Rough Electric
FE Moran
- Rough gas piping
- Welding gas pipe on roof
- Temp control guy to get started
M/I
- Splice detail per S3.00 detail 5
- Lintel at East end to be installed
Mastership – complete in 2 weeks
- Working on brick on north elevation
- Stone sills being installed
- Brick wash in courtyard
- NEED FRP DOORS-Hargrave
- CMU walls in MPR on rain days
AJ Oleson
- Start on courtyard downspout connections(3/4 days)
Maddon Glass
- Get started working behind the brick washer installing frames/glass by end of week or early next
Hargrave
- May have to take some temp board up down, but I will confirm once I know.
Week of 12/13/21 - 12/18/21
DCG/Filotto/Alloy
- Alloy metal wall panels
- Filotto should be almost 100%
Maddon Glass
- Start setting frames/glass in courtyard behind the brick washer
Amber
- Mech Rough Overhead
Mastership
- Brick on east elevation
- Brick washer
Doherty
- Insulation of walls
- Drywall
Nelson
- Once Skylight framing is complete Nelson will get back onsite
Jensen’s
- Rough Plumbing
Carey
- Electric Rough
FE Moran
- Roughing Overhead
Week of 12/20/21 - 12/25/21
Week of 1/10/22 - 1/15/22
DCG/Alloy/Filotto
- Coping/Gutters etc. to start once weather is better
- Plywood for coping to start being installed sooner than later above storefronts
Doherty
- Drywall/Durarock
- Taping/Sanding
- Insulation
- Paint Mockup
- Painter to start priming Monday
Hargrave
- Board up down Tuesday on North elevation
AMBER
- Move FCU’s in ELEC room and Resource room 116B ASAP -have answers
Jensen’s
- Overhead Rough
- Pipe Insulation
- Overflows in MPR to exterior
NELSON
- When looking for Inspection?
Carey
- Rough Electric Overhead
- NW corner rough
- Fire Alarm sub to start
FE Moran
- Piping to each fan coil unit
- Finish gas run into existing school at NW corner
Mastership
- Clean CMU prior to paint
- FRP doors holding up NW corner
- SF-L4 east end add more brick
- Waiting on confirmation date for sills
AJ Oleson
- Start on courtyard downspout connections (3/4days)
Maddon Glass
- Frames/Glass being installed northside
Week of 1/17/22 - 1/22/22
DCG/Filotto/Alloy
- Alloy metal wall panels to start weather dependent
Consolidated/Regency
- Should stop out this week to look
Maddon Glass
- Should be wrapping up end of week
Doherty
- Painting
- Durarock in bathrooms
- Drywall skylights
- Taping. /Mudding/ Sanding
- Alpine to start on grid in bathrooms
Jensen’s
- Rough Plumbing Overhead
Carey
- Electric Rough Overhead
FE Moran
- Roughing Overhead
Week of 1/24/22 - 1/29/22
**ALL trades to start fire caulking/sound caulking
DCG/Alloy/Filotto
- Coping/Gutters etc. to start once weather is better
- Plywood for coping to start being installed sooner than later above storefronts
Doherty
- Taping/Sanding/Mudding
- Painting
- Grid in classrooms (no secure to deck)
Consolidated
- Tile ongoing in bathrooms
AMBER
- Waiting for more grid to go up to start setting registers etc.
- Fire caulking penetrations
Jensen’s
- Overhead Rough
- Pipe Insulation ahead of grid
- Pipe labeling
- Fire/sound caulking
NELSON
- Start Fire caulking
- Remove labels off pipe in 3 rooms before paint (Painting end of week)
Carey
- Rough Electric Overhead
- MPR Rough to start back up after FA
FE Moran
- Condensate lines finish and insulate to FCU’s
- Prep for radiant ceiling tiles
- Finish run to NW corner
- Insulation of pipe
Mastership
- FRP doors holding up NW corner
- SF-L4 east end add more brick
- Waiting on confirmation date for sills
Maddon Glass
- Frames/Glass being caulked exterior and interior
Week of 1/31/22 - 2/5/22
DCG/Filotto/Alloy
- Wall panels once weather turns
Consolidated/Regency
- Tile in bathrooms
Doherty
- Painting MPR this week
- Sanding/Taping
- Alpine working on grid to move into classrooms
Nelson
- Start setting heads in grid behind the grid
Jensen’s
- Rough plumbing overhead
Carey
- Electric rough overhead
FE Moran/Amber
- Roughing overhead
- Ready for duct sock install end of week
Week of 2/7/22 - 2/12/22
DCG/Alloy/Filotto
- Coping/Gutters etc. to start once weather is better
- Plywood for coping to start being installed above storefronts
Doherty
- Taping/Sanding/Mudding almost wrapped up
- 1 day left to complete the paint in MPR
- Grid in corridors starting
- Skids of ceiling tiles being delivered
Consolidated
- Tile ongoing in bathrooms
- Waiting on purple tile
AMBER
- Fire caulking penetrations
- Setting registers in grid
Jensen’s
- Pipe Insulation
- Pipe labeling
- Fire/sound caulking
NELSON
- Setting heads in grid
Carey
- Lights delivery Monday
- Overhead rough
FE Moran
- Condensate lines finish and insulate to FCU’s
- Water on hot water pumps
- Hanging CAB units
- Insulation of pipe ongoing
Mastership
- SF-L4 east end add more brick
- Brick by FRP doors on hold
- Waiting on confirmation date for sills
Maddon Glass
- Frames/Glass being caulked exterior and interior
- Waiting on me for SF-L4 I need to pour more concrete
Week of 2/14/22 - 2/19/22
DCG/Filotto/Alloy
- Wall panels once weather turns
Consolidated/Regency
- Tile in bathrooms
Doherty
- Painting
- Alpine working on grid and hangers for lights
Nelson
- Setting heads
Jensen’s
- Rough Plumbing Overhead
Carey
- Electric Rough Overhead
FE Moran/Amber
- Roughing Overhead
- Ready for duct sock install end of week
Week of 2/21/22 - 2/26/22
Week of 2/28/22 - 3/5/22
DCG/Alloy/Filotto
- Coping/Gutters etc. to start once weather is better
- Plywood for coping to start being installed above storefronts
Doherty/Alpine
- Start dropping ceiling tiles once IMEG punch list is complete hopefully middle of week
NELSON
- FSCI is on the schedule for today 2-28
Carey
- Lights install
- Runs to electric room in existing school
- Working towards perm power over spring break
FE Moran
- Waiting on 6 correct valves to be delivered
MEPFP Overhead
- Inspections in classrooms and bathrooms passed
- Hallways/MPR/resource rooms to still be inspected
Mastership
- SF-L4 east end add more brick
- Brick by FRP doors
- Sill work
Maddon Glass
- Need doors for Curtain Walls
- Waiting on concrete stoop for SF-L4
- Other 2 window openings (SE corner tie in) won’t be until summer until we can demo the old
Week of 3/7/22 - 3/12/22
Week of 3/14/22 - 3/19/22
Week of 3/21/22 - 3/26/22
Consolidated
- Epoxy will finish this week
- Carpet and VCT should finish this week
Cibulka
- Look to start pouring stoops
AJ Oleson
- Water service work and maybe downspout work in courtyard
Carey
- ComEd
- Work on perm power for addition
Hargrave
- Cabinet /FEC’s/Toilet Accessories to deliver this week sometime
- Start install where is ready
Jensen’s
- Plumbing fixture delivery
Week of 4/4/22 - 4/9/22
DCG/Alloy/Filotto
- Coping/Gutters ongoing
- Wall Panels
- Plywood for coping installed above storefronts
M/I
- Out to install roof ladders
AJ
- Downspouts so we can start grading/pouring concrete
- Manholes covers to set everywhere
Albrecht/Cibulka
- Start second half of the week on grading
Doherty/Five Star
- Doherty to fix by grille for amber in storage room
Carey
- Trim work and disconnect trailer (Trailer picked up on 7th morning)
FE Moran
- RTU 1
Maddon Glass
- Interior glass for doors
- Caulk exterior Curtain Walls
- Waiting on me for SF-L4 I need to pour more concrete
- Other 2 window openings (SE corner tie in) won’t be until summer until we can demo the old
Hargrave
- Casework/cabinet Install
- Solid surface install
- Bathroom partition install
- FEC’s
Week of 4/11/22 - 4/16/22
Cibulka
- Start pouring stoops, walks, curbs
Hargrave
- Cabinet /FEC’s/Toilet Accessories
- Bathrooms partitions
- Solid surfacing
Jensen’s
- Once enough classroom cabinets are installed then get back out to start installing sinks
DCG/ALLOY
- Working on coping
Albrecht
- Grading
Maddon
- Set SF-L4 when concrete poured
Consolidated
- End of week beginning of next finish up base everywhere when cabinets complete
Week of 4/18/22 - 4/23/22
DCG/Alloy/Filotto
- Coping/Gutters
- Overflows to get tightened
Albrecht/Cibulka
- Working in courtyard on walks/curbs
- Albrecht grading and bringing stone in
Doherty/Five Star
- Doherty to fix by grille for amber in storage room
- Stencil fire rated wall at NW corner
- Frame chase at East Storefront-setting storefront Monday-should be ready to start framing Wednesday
Jensen’s
- Setting sinks in classrooms
- Downspouts
FE Moran
- JCI looking to start up FCU’s and setting thermostats
- Setting up RTU to be set right after school is out on June 2nd
Maddon Glass
- Interior glass for doors early in week
- Caulk exterior Curtain Walls
- SF-L4
Hargrave
- Wood doors and hardware to show up Tuesday
- Solid surface install
- Bathroom accessories ongoing
- FEC’s
- Kitchen Equipment
Consolidated
- Base
- Get epoxy material picked up
Week of 4/25/22 - 4/30/22
Week of 5/2/22 - 5/7/22
DCG/Alloy/Filotto
- Coping/Gutters
- 8 existing downspouts to get reworked
- Insulated Wall Panels
- Overflows to get tightened
- Finish roof at east end
Albrecht/Cibulka
- Working in courtyard on walks/curbs
- Albrecht grading up north and east
- Walks to start on north this week
- Meeting onsite for Courtyard (SEBERT/PLAYGROUND EQUIP)
Doherty/Five Star
- Stencil fire rated wall at NW corner
- Paint cast iron for downspouts to match the aged bronze
- Water fountain at NW the grey paint needs to wrap the bump outs
- Tape new chase built and grille patches
- Patch dings and paint touch up prior to the main Punchlist
Carey
- Exterior lights
- Applied/First Security missing some covers
- Panel schedules
- Horns in MPR to move
FE Moran
- JCI working on FCU’s and setting thermostats
- Covers for thermostats- JCI
- Looking to get gas to DOAS units
- Setting up RTU to be set right after school is out on June 2nd
Maddon Glass
- Caulk exterior Curtain Walls
Hargrave
- Wood doors and hardware to start
- FEC’s
- Grab bars
Week of 5/9/22 - 5/14/22
Cibulka/Albrecht/Sebert
- Cont. pouring stoops, walks, curbs
- Grading
- Playground Equipment should be onsite
- Landscaping to start and rubber surfacing post equipment
Doherty/Five Star/Alpine
- Grid to fix
- Make a few T’s removable for access to filters
- A lot of paint to touch up and just finish
FE Moran
- Gas to DOAS
Hargrave
- Wood doors
- Hardware
- GYM EQUIP
- Marker boards and tack boards this week
DCG/ALLOY
- Finish up coping and wait for insulated wall panels
Consolidated
- Finish VCT after FRP frames/doors are in
- Sealed concrete in JCI
Week of 5/16/22 - 5/21/22
DCG/Alloy/Filotto
- Coping/Gutters
- 8 existing downspouts to get reworked
- Insulated Wall Panels
- Overflows to get tightened
- Finish roof at east end
Albrecht/Cibulka/Sebert
- Working in courtyard landscaping
- Playground equipment
- Albrecht waiting on Cibulka so they can start spreading black for Sebert
- Walks to start on north
Doherty/Five Star
- Stencil fire rated wall at NW corner
- EM Seal after patch work
- Paint cast iron for downspouts to match the aged bronze
- Paint Precast
- Water fountain at NW the grey paint needs to wrap the bump outs
- Tape new chase built and grille patches
- Patch dings and paint touch up prior to the main Punchlist
- Returns after FRP frames are in
Mastership
- Send someone to recess the FEC missed in MPR
Consolidated
- Sealed concrete in JC
Carey
- Exterior lights
- Roller shades
- Horns in MPR to move
FE Moran
- JCI working on start up
- thermostats-
- Setting up RTU to be set right after school is out on June 2nd
Maddon Glass
- Caulk exterior Curtain Walls
Hargrave
- Ram board clean up before cleaners
- Doors and hardware
- FEC’s
- Grab bars
- Wood infill to match existing at NW tie in
Nelsons
- Set all heads flush with ceiling tile
Week of 5/23/22 - 5/28/22
Cibulka/Albrecht/Sebert
- Cont. pouring stoops, walks, curbs
- Grading
- Playground Equipment should be onsite
- Landscaping to start and rubber surfacing post equipment
Doherty/Five Star/Alpine
- Grid to fix
- Make a few T’s removable for access to filters
- A lot of paint to touch up and just finish
Carey
- Downspout melt system
- Hoops when arrive
Hargrave
- Cleaners Monday
- FRP to show up
- Hardware
- GYM EQUIP
- Marker boards and tack boards
DCG/ALLOY
- Insulated wall panels
Consolidated
- Finish VCT after FRP frames/doors are in
Week of 5/31/22 - 6/4/22
DCG/Alloy
- 8 existing downspouts to get reworked
- Insulated Wall Panels when delivered
- Overflows to get tightened
- Finish roof at east end
Albrecht/Cibulka/Sebert
- Rubber surfacing to start
- Walks on north side
Doherty/Five Star
- Stencil fire rated wall at NW corner
- Grid to be fixed/make some removable Ts for access to filters
- EM Seal after patch work
- Water fountain at NW the grey paint needs to wrap the bump outs
- Returns after FRP frames are in
Carey
- Exterior lights
- Roller shades
- Cages in MPR
- Snow Melt system-Gutters are complete
- Horns in MPR to move
FE Moran
- RTU to be set soon
Maddon Glass
- Caulk exterior Curtain Walls
Consolidated
- Finish VCT after FRP frames/doors are in -will follow up
Hargrave
- FRP
- Marker boards tack boards
- Grab bars
- Wood infill to match existing at NW tie in
- Basketball hoops
Nelsons
- Set all heads flush with ceiling tile
Phase 1 Project Scope
-
1 Story Building Addition & Sitework
-
8 Classrooms with Single User Toilets
-
4 Multi-User Toilets (Boys & Girls)
-
2 Single User Toilets
-
1 Multipurpose Room
-
Soft Play Surface & Mulch Courtyard with Trees
-
1 Storm Water Detention System
-
Landscaping
What can we expect?
The construction at Lyon School will add space for full-day kindergarten, include a multipurpose room addition, create a courtyard playground and update classrooms; as well as the following:
- ADA improvements
- Fire suppression sprinkler system throughout
- Partial roof replacement
- Interior and exterior maintenance
- Mechanical equipment replacement
- Galvanized piping replacement
- Lighting replacement throughout
- Electrical wiring, panel and service replacement
- Additional main office space
- Classroom environment (acoustic, flooring, other)
Phase 1 Timeline
February 2021
March 2021
May 2021
- Ground Breaking (May 17, 2021
- Construction Commencement (pending permit approvals)
August 2022
Frequently Asked Questions
- When will construction start and end?
- Will construction workers be inside the school building?
- What if construction noise impacts the classroom?
- Will construction dust impact the air quality in the classroom?
- Will our current parking be affected by the construction?
- What do I do if I see a safety issue?
When will construction start and end?
Will construction workers be inside the school building?
What if construction noise impacts the classroom?
Will construction dust impact the air quality in the classroom?
Will our current parking be affected by the construction?
What do I do if I see a safety issue?
Contact your school principal or Director of Operations Steve Ruelli.